AACE cost estimation classes (1–5)
Opnor's ECM cost estimates ship as AACE Class 4. That sounds like a contractual quirk — it isn't. AACE classes define how accurate a number is allowed to claim to be, and skipping a class because nobody asked you to specify is the most common way industrial projects come back with capex that's 50% over the audit number.
What AACE actually defines
AACE International (formerly the Association for the Advancement of Cost Engineering) publishes Recommended Practice 18R-97, which defines five cost estimate classes. Each class specifies:
- Project definition maturity — how much engineering work has been done before estimating
- Typical methodology — analogy / parametric / definitive
- Expected accuracy range — the +/- band the estimate is allowed to claim
- Use case — what business decision the estimate is supposed to support
It's a calibration framework, not a formula. The classes don't tell you what a VFD costs — they tell you what depth of pricing work the estimate is allowed to claim authority over.
The 5-class table
Why audits ship Class 4 (and what that means)
A 2-week audit can't produce a Class-3 estimate, full stop. Class 3 requires 10–40% project definition — that means an equipment list, vendor quotes for the major equipment, a preliminary contractor walk-through, and site-specific installation analysis. None of that fits inside a 2-week audit engagement.
What Opnor delivers in 2 weeks is Class 4: parametric cost estimates with equipment factored from a reference database, productivity multipliers for regional labour rates, and AACE-class contingency on top. That's accurate enough to make capital-screening decisions ("does this ECM clear our payback hurdle?") but not accurate enough to build a board AFE around without further refinement.
We're explicit about this in every audit deliverable: ECMs that pass the screening go to Class 3 estimation as a separate, paid engagement (typically 4–8 weeks per ECM, requires vendor engagement). Plants that bypass that step and try to commit capex against a Class-4 number are the ones that come back with overruns.
What Opnor includes in a Class-4 estimate
Every Class-4 ECM estimate includes the following lines:
Moving from Class 4 to Class 3
For ECMs that clear the screening and need budget-authorization-grade pricing, the path is roughly:
- Equipment-list refinement — get vendor quotes for the major equipment (typically the VFD, motor, heat exchanger, or compressor that drives the ECM)
- Site survey — contractor walk-through to identify field-condition issues (cable routing, structural mounting, demolition, refractory removal)
- Quantity refinement — actual cable runs, pipe lengths, demolition scope
- Labour productivity assessment — adjust regional rates for plant-specific access constraints (confined spaces, lockout-tagout, off-shift work)
- Schedule compression risk — Class 3 typically adds 5–15% premium for fast-track schedules
Opnor delivers Class 3 estimates as a separate engagement. We don't pad the 2-week audit deliverable to look Class-3 — it isn't, and pretending otherwise sets up the project for an overrun.
- Confirm Opnor's contingency default (currently 25% AACE Class-4 — verify in cost_engine/)
- Document the cost reference database — typical entry shape, refresh cadence, who maintains it
- Add a worked example: same VFD ECM at Class 4 vs Class 3 to show the difference